U.S. CMS Software and Computing
Work Breakdown Structure






Project Start:
Project Finish:



Tasks


<
WBS
Task Name
StartFinish Predecessors Resources % Complete
1
User Facility (UF)
    
1.1
Tier 1 Regional Center
FY2005FY2007 50 FTE years
1.1.1
Development and Test systems
FY2005FY2007 6 FTE years
1.1.1.1
Modular Test Stands
FY2005FY2005 0.5 FTE years
1.1.1.1.1
Offline Storage
FY2005FY2005 0.125 FTE years
1.1.1.1.2
Online Storage
FY2005FY2005 0.125 FTE years
1.1.1.1.3
Data Distribution Server
FY2005FY2005 0.125 FTE years
1.1.1.1.4
Software Build Machine
FY2005FY2005 0.125 FTE years
1.1.1.2
Integration Test Stand
FY2005FY2007 5.5 FTE years
1.1.1.2.1
Hardware
FY2005FY2005 0.75 FTE years
1.1.1.2.1.1
Hardware System Design
FY2005FY2005 0.125 FTE years
1.1.1.2.1.2
Integration Test Stand Hardware
FY2005FY2005 0.625 FTE years
1.1.1.2.1.2.1
Procurement
FY2005FY2005 0.125 FTE years
1.1.1.2.1.2.2
Installation & Commissioning
FY2005FY2005 0.5 FTE years
1.1.1.2.2
Software Deployment and Integration
FY2005FY2007 4.75 FTE years
1.1.1.2.2.1
Distributed Data Management (SW)
FY2005FY2007 1.25 FTE years
1.1.1.2.2.1.1
Software Deployment & Devel.
FY2005FY2007 0.75 FTE years
1.1.1.2.2.1.2
Maintenance
FY2006FY2007 0.5 FTE years
1.1.1.2.2.2
Distributed Data Access (SW)
FY2005FY2007 1.25 FTE years
1.1.1.2.2.2.1
Software Development
FY2005FY2006 0.5 FTE years
1.1.1.2.2.2.2
Maintenance
FY2006FY2007 0.75 FTE years
1.1.1.2.2.3
Monitoring Tools
FY2005FY2007 2.25 FTE years
1.1.1.2.2.3.1
Data Access Monitoring
FY2005FY2005 0.25 FTE years
1.1.1.2.2.3.1.1
Maintenance
FY2006FY2007 0.5 FTE years
1.1.1.2.2.3.2
Network Monitoring
FY2005FY2005 0.25 FTE years
1.1.1.2.2.3.2.1
Maintenance
FY2006FY2007 0.5 FTE years
1.1.1.2.2.3.3
Systems Monitoring
FY2005FY2005 0.25 FTE years
1.1.1.2.2.3.3.1
Maintenance
FY2006FY2007 0.5 FTE years
1.1.2
Simulation & Reconstruction systems
FY2005FY2007 8.875 FTE years
1.1.2.1
Hardware
FY2005FY2007 5 FTE years
1.1.2.1.1
Procurement
FY2005FY2007 0.75 FTE years
1.1.2.1.2
Installation & Commissioning
FY2005FY2007 3 FTE years
1.1.2.1.3
Hardware Maintenance
FY2005FY2007 1.25 FTE years
1.1.2.2
Software
FY2005FY2007 2 FTE years
1.1.2.2.1
Deployment & Development
FY2005FY2007 1.25 FTE years
1.1.2.2.2
Software Maintenance
FY2005FY2007 0.75 FTE years
1.1.2.3
System Administration
FY2005FY2007 1.875 FTE years
1.1.3
Analysis Systems
FY2005FY2007 16.75 FTE years
1.1.3.1
Hardware
FY2005FY2007 6.375 FTE years
1.1.3.1.1
Procurement
FY2005FY2007 1.25 FTE years
1.1.3.1.2
Installation & Commissioning
FY2005FY2007 3.5 FTE years
1.1.3.1.3
Hardware Maintenance
FY2005FY2007 1.625 FTE years
1.1.3.2
Software
FY2005FY2007 2.625 FTE years
1.1.3.2.1
Deployment & Development
FY2005FY2007 1.625 FTE years
1.1.3.2.2
Software Maintenance
FY2006FY2007 1 FTE years
1.1.3.3
System Administration
FY2005FY2007 7.75 FTE years
1.1.4
Data Access and Distribution Servers
FY2005FY2007 3.5 FTE years
1.1.4.1
Hardware
FY2005FY2007 1.5 FTE years
1.1.4.1.1
Procurement
FY2005FY2007 0.375 FTE years
1.1.4.1.2
Installation & Commissioning
FY2005FY2007 0.5 FTE years
1.1.4.1.3
Hardware Maintenance
FY2005FY2007 0.625 FTE years
1.1.4.2
Software
FY2005FY2007 2 FTE years
1.1.4.2.1
Local Software
FY2005FY2007 0.75 FTE years
1.1.4.2.1.1
Deployment & Development
FY2005FY2007 0.5 FTE years
1.1.4.2.1.2
Software Maintenance
FY2006FY2007 0.25 FTE years
1.1.4.2.2
GRID Software
FY2005FY2007 1.25 FTE years
1.1.4.2.2.1
Deployment & Development
FY2005FY2007 0.75 FTE years
1.1.4.2.2.2
SoftwareMaintenance
FY2006FY2007 0.5 FTE years
1.1.4.3
System Administration
    
1.1.5
Calibration and Non-Event Database Servers
FY2005FY2007 2.125 FTE years
1.1.5.1
Hardware
FY2005FY2007 0.75 FTE years
1.1.5.2
Software
FY2005FY2007 0.75 FTE years
1.1.5.3
System Administration
FY2005FY2007 0.625 FTE years
1.1.6
Data Storage Systems
FY2005FY2007 5.75 FTE years
1.1.6.1
Tape Data Storage System
FY2005FY2007 5.75 FTE years
1.1.6.1.1
Procurement and installation
FY2005FY2007 2.5 FTE years
1.1.6.1.2
Storage System Interface Development:
FY2005FY2007 0.75 FTE years
1.1.6.1.3
Archive Administration O & M
FY2005FY2007 2.5 FTE years
1.1.6.1.3.1
Ewuipment Maintenance
FY2005FY2007 0.375 FTE years
1.1.6.1.3.2
Tape Maintenance
FY2005FY2007 0.375 FTE years
1.1.6.1.3.3
Media Upgrades
    
1.1.6.1.3.4
Software and Configuration Updates
FY2005FY2007 0.375 FTE years
1.1.6.1.3.5
Routine Administration
FY2005FY2007 0.375 FTE years
1.1.6.1.3.6
Operations Documentation
FY2005FY2007 1 FTE years
1.1.6.1.3.6.1
Develop initial methods
FY2005FY2006 0.75 FTE years
1.1.6.1.3.6.2
Maintain methods
FY2006FY2007 0.25 FTE years
1.1.7
Data import/export
FY2005FY2007 4.125 FTE years
1.1.7.1
Tape import/export
FY2005FY2007 2.375 FTE years
1.1.7.1.1
Facility Planning
FY2005FY2005 0.125 FTE years
"1.1.7.1.2
Procurement, Installation & Conf.
FY2005FY2007 1 FTE years
1.1.7.1.2.1
Tape Technology
FY2005FY2007 0.5 FTE years
1.1.7.1.2.2
Tape Import/export method planning
FY2005FY2007 0.5 FTE years
1.1.7.1.2.2.1
Initial development
FY2005FY2005 0.25 FTE years
1.1.7.1.2.2.2
Maintenance
FY2006FY2007 0.25 FTE years
1.1.7.1.3
Tape Import/export operations
FY2005FY2007 1.25 FTE years
1.1.7.2
Network Import/export
FY2005FY2007 1.75 FTE years
1.1.7.2.1
Planning
FY2005FY2007 0.5 FTE years
1.1.7.2.2
Interface Software
FY2005FY2007 0.5 FTE years
1.1.7.2.3
Ingest/Export production
FY2005FY2007 0.75 FTE years
1.1.8
Data and Physics Analysis Software
FY2005FY2007 2.875 FTE years
1.1.8.1
Deployment
FY2005FY2007 1.25 FTE years
1.1.8.2
Maintenance
FY2006FY2007 0.25 FTE years
1.1.8.3
Licenses
FY2005FY2007 0.375 FTE years
1.1.8.4
User Support
FY2005FY2007 1 FTE years
1.2
System and User Support
FY2000FY2007 23.8125 FTE years
1.2.1
Documentation
FY2000FY2007 4.5 FTE years
1.2.2
Collaborative Tools
FY2000FY2007 3.875 FTE years
1.2.3
Development Environment
FY2000FY2007 4.375 FTE years
"1.2.4
Administration, Monitoring + Problem Resolution Software
FY2001FY2007 2.8125 FTE years
1.2.4.1
User administration tools
FY2001FY2007 0.6625 FTE years
1.2.4.2
Resource allocation and tracking tools
FY2001FY2007 0.8875 FTE years
1.2.4.3
Resource/process monitoring tools
FY2001FY2007 1.2625 FTE years
1.2.5
User Help Desk
FY2001FY2007 1.75 FTE years
1.2.5.1
Problem tracking tool
FY2001FY2007 1.1625 FTE years
1.2.5.2
Staffing of helpdesk
FY2001FY2007 0.5875 FTE years
1.2.6
Training Office
FY2000FY2007 1.875 FTE years
1.2.6.1
User Training
FY2000FY2007 1 FTE years
1.2.6.2
Training support staff
FY2001FY2007 0.875 FTE years
1.2.7
Support for Tier 2 Centers
FY2000FY2007 2 FTE years
1.2.7.1
Software Installations
FY2000FY2007 1.0625 FTE years
1.2.7.2
Systems Consulting
FY2000FY2007 0.9375 FTE years
1.2.8
Computer Security
FY2001FY2007 2.625 FTE years
1.2.8.1
Password Security
FY2001FY2007 1.3125 FTE years
1.2.8.2
Operating System Security
FY2001FY2007 0.8125 FTE years
1.2.8.3
Access Auditing
FY2004FY2007 0.5 FTE years
1.3
Operations and Infrastructure
FY2000FY2007 17.75 FTE years
1.3.1
Software license maintenance
FY2001FY2007 4.125 FTE years
1.3.1.1
Software license tracking (central systems)
FY2001FY2007 1.25 FTE years
1.3.1.2
Software license tracking (PCs/desktops)
FY2002FY2007 2.875 FTE years
1.3.2
Systems Operation
FY2001FY2007 10.5 FTE years
1.3.2.1
Data center operations
FY2001FY2007 4.375 FTE years
1.3.2.1.1
Operate data center
FY2001FY2007 3.625 FTE years
1.3.2.1.2
Shipping tapes offsite
FY2006FY2007 0.5 FTE years
1.3.2.1.3
Tapecopy facility operations
FY2006FY2007 2 FTE years
1.3.3
Infrastructure support
FY2000FY2007 3.125 FTE years
1.3.3.1
Power support
FY2001FY2007 1.375 FTE years
1.3.3.2
Space planning
FY2001FY2007 1.625 FTE years
1.3.3.2.1
Offices
FY2001FY2007 0.8125 FTE years
1.3.3.2.2
Computer floor
FY2002FY2007 0.8125 FTE years
1.4
Tier 2 Regional Centers -- WBS 1.4 (Tier-2 centers) is not yet updated!!!!
FY2001FY2007 36.5 FTE years
1.4.1
Tier 2 Center 1
FY2000FY2007 11.5 FTE years
1.4.1.1
T2 Design
FY2000FY2001 0.375 FTE years
1.4.1.2
T2 Equipment
FY2000FY2007 4.625 FTE years
1.4.1.2.1
Hardware Procurement & Installation
FY2000FY2007 0.875 FTE years
1.4.1.2.2
Commissioning
FY2001FY2007 1.75 FTE years
1.4.1.2.3
Hardware Maintenance
FY2002FY2007 1.5 FTE years
1.4.1.3
T2 Software Infrastructure Framework
FY2000FY2007 3.875 FTE years
1.4.1.3.1
Installation and Deployment
FY2000FY2007 2.25 FTE years
1.4.1.3.2
Maintenance
FY2000FY2007 1.625 FTE years
1.4.1.4
Integration with T1/T2
FY2001FY2007 2 FTE years
1.4.1.5
System Documentation
FY2001FY2007 0.875 FTE years
1.4.2
Tier 2 Center 2
FY2001FY2007 9.5 FTE years
1.4.2.1
T2 Design
FY2000FY2001 12.25 FTE years
1.4.2.2
T2 Equipment
FY2001FY2007 3.75 FTE years
1.4.2.2.1
Hardware Procurement & Installation
FY2001FY2007 0.75 FTE years
1.4.2.2.2
Commissioning
FY2001FY2007 1.75 FTE years
1.4.2.2.3
Hardware Maintenance
FY2003FY2007 1.25 FTE years
1.4.2.3
T2 Software Infrastructure Framework
FY2001FY2007 3.125 FTE years
1.4.2.3.1
Installation and Deployment
FY2001FY2007 1.75 FTE years
1.4.2.3.2
Maintenance
FY2002FY2007 1.375 FTE years
1.4.2.4
Integration with T1/T2
FY2001FY2007 1.75 FTE years
1.4.2.5
System Documentation
FY2002FY2007 0.75 FTE years
1.4.2
Tier 2 Center 3
FY2002FY2007 7.5 FTE years
1.4.2.1
T2 Design
FY2000FY2002 12.25 FTE years
1.4.2.2
T2 Equipment
FY2002FY2007 3 FTE years
1.4.2.2.1
Hardware Procurement & Installation
FY2002FY2007 0.75 FTE years
1.4.2.2.2
Commissioning
FY2002FY2007 1.5 FTE years
1.4.2.2.3
Hardware Maintenance
FY2005FY2007 0.75 FTE years
1.4.2.3
T2 Software Infrastructure Framework
FY2002FY2007 2.5 FTE years
1.4.2.3.1
Installation and Deployment
FY2002FY2007 1.5 FTE years
1.4.2.3.2
Maintenance
FY2003FY2007 1 FTE years
1.4.2.4
Integration with T1/T2
FY2002FY2007 1.25 FTE years
1.4.2.5
System Documentation
FY2003FY2007 0.625 FTE years
1.4.2
Tier 2 Center 4
FY2004FY2007 5 FTE years
1.4.2.1
T2 Design
FY2000FY2004 7 FTE years
1.4.2.2
T2 Equipment
FY2004FY2007 2 FTE years
1.4.2.2.1
Hardware Procurement & Installation
FY2004FY2007 0.5 FTE years
1.4.2.2.2
Commissioning
FY2004FY2007 1 FTE years
1.4.2.2.3
Hardware Maintenance
FY2006FY2007 0.5 FTE years
1.4.2.3
T2 Software Infrastructure Framework
FY2004FY2007 1.625 FTE years
1.4.2.3.1
Installation and Deployment
FY2004FY2007 1 FTE years
1.4.2.3.2
Maintenance
FY2005FY2007 0.625 FTE years
1.4.2.4
Integration with T1/T2
FY2004FY2007 0.875 FTE years
1.4.2.5
System Documentation
FY2005FY2007 0.375 FTE years
1.4.2
Tier 2 Center 5
FY2005FY2007 4 FTE years
1.4.2.1
T2 Design
FY2000FY2005 3.875 FTE years
1.4.2.2
T2 Equipment
FY2005FY2007 1.625 FTE years
1.4.2.2.1
Hardware Procurement & Installation
FY2005FY2007 0.375 FTE years
1.4.2.2.2
Commissioning
FY2005FY2007 0.75 FTE years
1.4.2.2.3
Hardware Maintenance
FY2006FY2007 0.5 FTE years
1.4.2.3
T2 Software Infrastructure Framework
FY2005FY2007 1.25 FTE years
1.4.2.3.1
Installation and Deployment
FY2005FY2007 0.75 FTE years
1.4.2.3.2
Maintenance
FY2006FY2007 0.5 FTE years
1.4.2.4
Integration with T1/T2
FY2005FY2007 0.75 FTE years
1.4.2.5
System Documentation
FY2006FY2007 0.25 FTE years
1.5
Networking
FY2000FY2007 15.5 FTE years
1.5.1
Onsite network infrastructure
FY2000FY2007 6.75 FTE years
1.5.1.1
Network design
FY2000FY2007 2.375 FTE years
1.5.1.2
Procurement and implementation
FY2000FY2007 2.125 FTE years
1.5.1.3
Operational network support
FY2001FY2007 2.25 FTE years
1.5.2
Offsite network support
FY2002FY2007 2.375 FTE years
1.5.2.1
CERN connectivity
FY2003FY2007 0.625 FTE years
1.5.2.2
US-CMS connectivity
FY2002FY2007 0.75 FTE years
1.5.2.3
Data grid network services
FY2004FY2007 1 FTE years
1.5.3
Network security
FY2002FY2007 3.125 FTE years
1.5.3.1
Onsite network security
FY2002FY2007 1.375 FTE years
1.5.3.2
Offsite network security
FY2004FY2007 1.75 FTE years
1.5.4
Network performance monitoring
FY2003FY2007 3.25 FTE years
1.5.4.1
Onsite mon. and troubleshooting
FY2003FY2007 1.25 FTE years
1.5.4.2
Offsite mon. and troubleshooting
FY2003FY2007 2 FTE years
1.6
Computing and Software R&D
FY2000FY2007 16.8125 FTE years
1.6.1
Distributed Data and Computing Test Beds
FY2000FY2004 2.375 FTE years
1.6.1.1
Hardware Testbed system design
FY2000FY2004 0.3125 FTE years
1.6.1.2
Hardware Testbed system
FY2000FY2004 0.625 FTE years
1.6.1.2.1
Procurement
FY2000FY2004 0.3125 FTE years
1.6.1.2.2
Installation & Commissioning
FY2000FY2004 0.3125 FTE years
1.6.1.3
Distributed Data Management (SW)
FY2000FY2004 0.5625 FTE years
1.6.1.3.1
Software Development
FY2000FY2004 0.5 FTE years
1.6.1.3.2
Maintenance
FY2004FY2004 0.0625 FTE years
1.6.1.4
Distributed Data Access (SW)
FY2000FY2004 0.3125 FTE years
1.6.1.4.1
Software Development
FY2000FY2003 0.25 FTE years
1.6.1.4.2
Maintenance
FY2004FY2004 0.0625 FTE years
1.6.1.5
Monitoring Tools
FY2000FY2004 0.5625 FTE years
1.6.1.5.1
Data Access Monitoring
FY2000FY2004 0.875 FTE years
1.6.1.5.2
Systems Monitoring
FY2001FY2004 0.625 FTE years
1.6.2
R&D in Computing Hardware for T1/T2
FY2000FY2007 8.125 FTE years
1.6.2.1
Technology Tracking and Testing
FY2000FY2007 1.875 FTE years
1.6.2.2
Technology Investigation and Deployment
FY2000FY2004 6.25 FTE years
1.6.2.2.1
Data Intensive Computing
FY2001FY2004 2.25 FTE years
1.6.2.2.1.1
Procurement & Installation
FY2001FY2004 0.375 FTE years
1.6.2.2.1.2
Commissioning
FY2001FY2004 0.375 FTE years
1.6.2.2.1.3
System Infrastructure Software
FY2001FY2004 1.5 FTE years
1.6.2.2.1.3.1
Interactive Cluster Software
FY2001FY2004 0.625 FTE years
1.6.2.2.1.3.1.1
Software Deployment
FY2001FY2004 0.625 FTE years
1.6.2.2.1.3.1.2
Maintenance
    
1.6.2.2.1.3.2
Batch Cluster Software
FY2001FY2004 0.4375 FTE years
1.6.2.2.1.3.2.1
Software Deployment
FY2001FY2004 0.5 FTE years
1.6.2.2.1.3.2.2
Maintenance
    
1.6.2.2.1.3.3
System Monitoring Software
FY2001FY2004 0.4375 FTE years
1.6.2.2.1.3.3.1
Software Deployment
FY2001FY2004 0.5 FTE years
1.6.2.2.1.3.3.2
Software Maintenance
    
1.6.2.2.2
CPU Intensive Computing
FY2000FY2004 2.5 FTE years
1.6.2.2.2.1
Procurement,Installation & Commissioning
FY2000FY2004 0.625 FTE years
1.6.2.2.2.2
Systems Infrastructure Software
FY2000FY2004 1.875 FTE years
1.6.2.2.2.2.1
Batch Cluster Software Maint
FY2000FY2004 0.4375 FTE years
1.6.2.2.2.2.2
Aut. Job Handling Framework
FY2000FY2004 0.4375 FTE years
1.6.2.2.2.2.3
System Monitoring Software Maint
FY2000FY2004 0.5 FTE years
1.6.2.2.2.2.4
CMS software environment
FY2000FY2004 0.5 FTE years
1.6.2.2.3
Data Access and Distribution Servers
FY2001FY2004 1.5 FTE years
1.6.2.2.3.1
Procurement & Installation
FY2001FY2004 0.3125 FTE years
1.6.2.2.3.2
Commissioning
FY2001FY2004 0.3125 FTE years
1.6.2.2.3.3
System Infrastructure Software
FY2001FY2004 0.875 FTE years
1.6.2.2.3.3.1
Software Deployment
FY2001FY2004 0.875 FTE years
1.6.2.2.3.3.2
Software Maintenance
FY2004FY2004 0.125 FTE years
1.6.3
Prototype Fully Functional Regional Center
FY2001FY2004 2.6875 FTE years
1.6.3.1
Prototype Regional Center Design
FY2001FY2004 0.75 FTE years
1.6.3.2
Prototype Regional Center
FY2003FY2004 1.9375 FTE years
1.6.3.2.1
Hardware Procurement & Installation
FY2003FY2004 0.375 FTE years
1.6.3.2.2
Commissioning
FY2003FY2004 0.375 FTE years
1.6.3.2.3
Software Infrastructure Framework
FY2003FY2004 0.3125 FTE years
1.6.3.2.3.1
Installation and Deployment
FY2003FY2004 0.3125 FTE years
1.6.3.2.3.2
Maintenance
    
1.6.3.2.4
Integration with Other Centers (T0/T2)
FY2003FY2004 0.5625 FTE years
1.6.3.2.5
System Documentation
FY2003FY2004 0.3125 FTE years
1.6.4
Simulation Software
FY2001FY2007 3.125 FTE years
1.6.4.1
Simulation Validation
FY2001FY2007 1.375 FTE years
1.6.4.2
Distributed Computing Model
FY2001FY2007 0.875 FTE years
1.6.4.3
Tier 1 Regional Center Simulations
FY2001FY2007 0.875 FTE years
1.6.5
System Administration
FY2000FY2004 0.625 FTE years
1.7
Detector Construction Phase Computing
FY2000FY2005 8.75 FTE years
1.7.1
CMS Computing Facility
FY2000FY2004 1.375 FTE years
1.7.1.1
Procurement , Installation,Comm,Maint.
FY2000FY2004 0.625 FTE years
1.7.1.2
Software installation & maintenance
FY2000FY2004 0.75 FTE years
1.7.2
Data Storage System
FY2000FY2005 2 FTE years
1.7.2.1
Procurement of extra capacity
FY2001FY2004 0.25 FTE years
1.7.2.2
Extra administration
FY2000FY2004 0.375 FTE years
1.7.2.3
Software Interface
FY2000FY2004 1.125 FTE years
1.7.2.4
Export data to final system
FY2005FY2005 0.25 FTE years
1.7.3
Network based file interchange
FY2001FY2004 1.5 FTE years
1.7.3.1
Planning
FY2001FY2004 0.5 FTE years
1.7.3.2
Software
FY2001FY2004 0.5 FTE years
1.7.3.3
Production
FY2001FY2004 0.5 FTE years
1.7.4
Tape import/export
FY2001FY2004 1.625 FTE years
1.7.4.1
Planning/coordination
FY2001FY2004 0.5 FTE years
1.7.4.2
Procurement
FY2001FY2001 0.125 FTE years
1.7.4.3
Software
FY2001FY2004 0.5 FTE years
1.7.4.4
Production
FY2001FY2004 0.5 FTE years
1.7.5
System Administration
FY2000FY2004 2.25 FTE years
1.8
Support for FNAL based computing
FY2000FY2007 11.875 FTE years
1.8.1
Desktop systems
FY2000FY2007 8.625 FTE years
1.8.1.1
Installation
FY2001FY2007 2.625 FTE years
1.8.1.1.1
System specifiation, design,installation
FY2001FY2007 1 FTE years
1.8.1.1.2
Host server systems
FY2001FY2007 1 FTE years
1.8.1.1.3
Backup systems
FY2002FY2007 0.625 FTE years
1.8.1.1.3.1
System specification and selection
FY2002FY2004 0.1875 FTE years
1.8.1.1.3.2
Installation and setup
FY2002FY2007 0.4375 FTE years
1.8.1.2
Support
FY2000FY2007 4.75 FTE years
1.8.1.3
User data storage and archiving
FY2002FY2007 1.25 FTE years
1.8.1.3.1
System specification and design
FY2002FY2002 0.25 FTE years
1.8.1.3.2
Installation,deployment,maintenance
FY2002FY2007 1 FTE years
1.8.2
Remote Control Room
FY2003FY2007 3.25 FTE years
1.8.2.1
Hardware
FY2003FY2007 1.25 FTE years
1.8.2.1.1
Procurement, Installation & Comm
FY2003FY2004 0.5 FTE years
1.8.2.1.2
Maintenance
FY2005FY2007 0.75 FTE years
1.8.2.2
Software
FY2003FY2007 2 FTE years
1.8.2.2.1
Deployment & Development
FY2003FY2005 1.5 FTE years
2
Core Application Software (CAS)
Fri 1/1/99Mon 7/18/05  0%
2.1
Software Architecture
Mon 5/1/00Wed 12/24/03  0%
2.1.1
Overall Achitecture and Framework
Mon 5/1/00Fri 9/1/00  0%
2.1.2
Subsystem Architectures
Mon 9/4/00Wed 12/24/03  0%
2.1.2.1
Detector Description Sub-Architecture
Mon 9/4/00Fri 1/3/03  0%
2.1.2.1.1
Evaluation of XML
Mon 9/4/00Wed 2/28/01 UC Davis SW Eng.1[75%]0%
2.1.2.1.2
Release of Tools for conversion from GEANT3 Format to XML
Thu 3/1/01Thu 3/1/017 0%
2.1.2.1.3
Test Beam Evaluation Prototype
Fri 3/2/01Thu 7/19/018UC Davis SW Eng.1[75%]0%
2.1.2.1.4
Assessment of XML Technology
Fri 7/20/01Fri 7/20/019 0%
2.1.2.1.5
DDD Development
Mon 7/23/01Fri 11/2/0110UC Davis SW Eng.1[75%]0%
2.1.2.1.6
Release of DDD Prototype
Mon 11/5/01Mon 11/5/0111 0%
2.1.2.1.7
Evaluation of User Interface and Calibration Study
Tue 11/6/01Fri 3/1/0212UC Davis SW Eng.1[25%]0%
2.1.2.1.8
Release of User Evaluation and Calibration Recommendation
Mon 3/4/02Mon 3/4/0213 0%
2.1.2.1.9
DDD to IGUANA Interface Development
Tue 11/6/01Fri 3/1/0212UC Davis SW Eng.1[50%]0%
2.1.2.1.10
DDD Second Prototype Development
Mon 3/4/02Fri 1/3/0315UC Davis SW Eng.1[75%]0%
2.1.2.2
OSCAR Code Librarian
Tue 5/1/01Mon 12/23/02 Fermilab SW Eng.1 [25%]0%
2.1.2.3
Reconstruction Sub-Architecture
Thu 2/1/01Wed 12/24/03  0%
2.1.2.3.1
Calorimeter Architectural Development
Thu 2/1/01Wed 12/24/03  0%
2.1.2.3.1.1
Initial Code Assessment
Thu 2/1/01Tue 2/20/01 Caltech SW Eng.2 [25%]0%
2.1.2.3.1.2
Code Ported to new compiler
Wed 2/21/01Wed 2/21/0120 0%
2.1.2.3.1.3
Removal of Obsolete Code
Thu 2/22/01Wed 4/11/0121Caltech SW Eng.2 [25%]0%
2.1.2.3.1.4
Initial Design of Calorimetry Code
Fri 6/1/01Mon 7/2/01 Caltech SW Eng.2 [50%]0%
2.1.2.3.1.5
Release of design for PRS and CARF groups for comment
Tue 7/3/01Tue 7/3/0123 0%
2.1.2.3.1.6
Basic Implementation of new design
Wed 7/4/01Mon 10/15/0124Caltech SW Eng.2 [50%]0%
2.1.2.3.1.7
Release of code for use in production
Tue 10/16/01Tue 10/16/0125 0%
2.1.2.3.1.8
Implementation of the Generation and Storage of Raw Calorimetry Data
Wed 10/17/01Tue 12/18/0126Caltech SW Eng.2 [50%]0%
2.1.2.3.1.9
Release of Calorimetry Code (Phase 1-4)
Wed 12/19/01Wed 12/19/0127 0%
2.1.2.3.1.10
Software Maintanence M&O
Thu 12/20/01Wed 12/24/0328Caltech SW Eng.2 [25%]0%
2.1.2.4
Analysis Sub-Architecture/Framework
Fri 12/1/00Thu 11/21/02  0%
2.1.2.4.1
Use case analysis
Fri 12/1/00Fri 2/9/01 Northeastern SW Eng.2[50%]0%
2.1.2.4.2
Analysis sub-architecture and kernel
Mon 2/12/01Fri 9/28/0131Northeastern SW Eng.2[50%]0%
2.1.2.4.3
Analysis architecture/ kernel defined for FFP
Wed 10/31/01Wed 10/31/0132 0%
2.1.2.4.4
Analysis architecture / kernel / framework development
Thu 11/1/01Thu 11/21/0233Northeastern SW Eng.2[50%]0%
2.1.2.5
Production Framework
Thu 11/1/01Fri 12/27/02  0%
2.1.2.5.1
Evaluation and Split from CARF
Thu 11/1/01Wed 1/9/02 Fermilab SW Eng.2 [25%],Princeton SW Eng.1[25%]0%
2.1.2.5.2
Release of Design
Thu 1/10/02Thu 1/10/0236 0%
2.1.2.5.3
Initial Development
Fri 1/11/02Thu 4/4/0237Princeton SW Eng.1[25%],Fermilab SW Eng.2 [25%]0%
2.1.2.5.4
Deployment for use in Production
Fri 4/5/02Fri 4/5/0238 0%
2.1.2.5.5
Production Framework Development
Mon 4/8/02Fri 12/27/0239Fermilab SW Eng.2 [40%],Princeton SW Eng.1[25%]0%
2.1.3
CMS architecture forum and evaluation (CAFÉ)
Mon 5/1/00Thu 12/5/02  0%
2.1.3.1
Architectural Publishing Tools
Mon 5/1/00Wed 12/4/02  0%
2.1.3.1.1
Document repository
Mon 5/1/00Thu 6/1/00 Northeastern SW Eng.2[25%]0%
2.1.3.1.2
Document templates
Wed 5/31/00Thu 11/30/00 Northeastern SW Eng.2[10%]0%
2.1.3.1.3
Multi-document build system
Mon 5/1/00Wed 2/14/01 Northeastern SW Eng.2[15%]0%
2.1.3.1.4
Web hosting
Mon 10/2/00Fri 11/24/00 Northeastern SW Eng.2[15%]0%
2.1.3.1.5
First version of CAFÉ tools
Thu 3/1/01Thu 3/1/0143,44,45,46 0%
2.1.3.1.6
Architectural Publishing Tool M&O
Fri 3/2/01Wed 12/4/0247Northeastern SW Eng.2[5%]0%
2.1.3.2
Domain Analysis
Mon 7/3/00Thu 12/5/02  0%
2.1.3.2.1
Top-level documentation of current status
Mon 7/3/00Tue 5/1/01  0%
2.1.3.2.1.1
Documentation of existing use cases, scenarios, requirements, etc.
Mon 7/3/00Mon 9/25/00 Northeastern SW Eng.2[15%]0%
2.1.3.2.1.2
Top-level analysis requirements document
Tue 9/26/00Tue 9/26/0051 0%
2.1.3.2.1.3
Documentation of "Functional Prototype" Software
Mon 8/14/00Mon 4/30/01 Northeastern SW Eng.2[10%]0%
2.1.3.2.1.4
Top-level architectural description document
Tue 5/1/01Tue 5/1/0153 0%
2.1.3.2.2
Sub-system documentation
Mon 12/3/01Tue 4/23/02  0%
2.1.3.2.2.1
Calorimetry architecture documentation
Mon 12/3/01Tue 4/23/02 Caltech SW Eng.2 [25%]0%
2.1.3.2.3
Design Evolution
Wed 5/2/01Thu 12/5/0254Northeastern SW Eng.2[20%]0%
2.2
Interactive Graphical User Analysis (IGUANA)
Thu 4/1/99Mon 5/5/03  0%
2.2.1
Graphical User Interface
Mon 5/3/99Mon 11/4/02  0%
2.2.1.1
GUI Toolkits
Mon 5/3/99Mon 8/2/99  0%
2.2.1.1.1
Low-level 2D graphics
Mon 5/3/99Fri 5/28/99  0%
2.2.1.1.2
Legacy GUI's (support)
Mon 5/3/99Mon 8/2/99  0%
2.2.1.1.3
GUI toolkit evaluations
Mon 5/3/99Thu 7/29/99  0%
2.2.1.1.4
Qt / Xt mixing
Thu 7/1/99Thu 7/29/99  0%
2.2.1.1.5
Select GUI toolkit baseline
Mon 8/2/99Mon 8/2/9962,63,64 0%
2.2.1.2
Widget Extension Libraries
Wed 8/4/99Mon 2/5/01  0%
2.2.1.2.1
Custom widgets: trees,tables,… (develop)
Wed 8/4/99Wed 9/1/9965Northeastern SW Eng. 1 [10%]0%
2.2.1.2.2
Technical widgets (import and evaluate)
Mon 9/6/99Mon 10/4/9965Northeastern SW Eng. 1 [10%]0%
2.2.1.2.3
Evaluate Qt table
Mon 1/8/01Mon 2/5/01  0%
2.2.1.3
Application Widgets
Tue 8/3/99Tue 10/31/00  0%
2.2.1.3.1
Sheet, document, window MDI
Tue 8/3/99Wed 9/1/9965 0%
2.2.1.3.2
Multi-document Interface (IgMDI)
Mon 5/1/00Thu 6/1/00 Northeastern SW Eng. 1 [25%]0%
2.2.1.3.3
Qt Workspace MDI
Fri 9/29/00Tue 10/31/00 Northeastern SW Eng. 1 [25%]0%
2.2.1.4
Graphical User Interface M&O
Mon 5/3/99Mon 11/4/02  0%
2.2.1.4.1
Graphical User Interface M&O (FP phase)
Mon 5/3/99Thu 10/12/00 Northeastern SW Eng. 1 [5%]0%
2.2.1.4.2
Graphical User Interface M&O (FFP phase)
Mon 10/16/00Mon 11/4/0275Northeastern SW Eng. 1 [10%]0%
2.2.1.4.3
Reconsideration of baseline GUI tools
Wed 10/31/01Wed 10/31/01  0%
2.2.2
Detector&Event Visualisation
Thu 4/1/99Mon 5/5/03  0%
2.2.2.1
Underlying Graphics
Mon 5/3/99Thu 3/1/01  0%
2.2.2.1.1
Low-level 3D graphics
Mon 5/3/99Mon 10/16/00  0%
2.2.2.1.2
High-level 3D graphics
Mon 5/3/99Mon 10/16/00  0%
2.2.2.1.3
Qt / OpenGL mixing
Tue 6/1/99Mon 8/2/99  0%
2.2.2.1.3.1
Qt / OpenGL mixing demonstration
Tue 6/1/99Mon 8/2/99  0%
2.2.2.1.4
Qt / OpenInventor mixing
Tue 6/1/99Mon 8/2/99  0%
2.2.2.1.4.1
Qt / OpenInventor mixing demonstration
Tue 6/1/99Mon 8/2/99  0%
2.2.2.1.5
Select 3D baseline (Functional Prototype)
Mon 8/2/99Mon 8/2/9965,83,85 0%
2.2.2.1.6
High-level 2D graphics
Thu 2/1/01Thu 3/1/01  0%
2.2.2.1.6.1
Evaluation
Thu 2/1/01Thu 3/1/01  0%
2.2.2.2
Viewers
Mon 5/3/99Mon 5/5/03  0%
2.2.2.2.1
Motif Detector / Event display
Mon 5/3/99Mon 8/2/99  0%
2.2.2.2.1.1
Port "Cmscan Classic" controller to new GUI toolkit
Mon 5/3/99Mon 8/2/99 Northeastern SW Eng. 1 [10%]0%
2.2.2.2.2
Interactive 3D viewers
Tue 8/3/99Mon 11/1/99  0%
2.2.2.2.2.1
Prototype 3D viewer
Tue 8/3/99Mon 11/1/99 Northeastern SW Eng. 1 [10%]0%
2.2.2.2.2.2
Generic 3D viewer with local interactivity
Mon 11/1/99Mon 11/1/9993 0%
2.2.2.2.3
3D Detector / Event display
Wed 8/18/99Fri 12/13/02  0%
2.2.2.2.3.1
Prototype Detector / Event Viewer
Wed 8/18/99Tue 10/31/00  0%
2.2.2.2.3.2
Benchmarking, testing, and performance enhancements
Mon 6/4/01Fri 12/13/02 Northeastern SW Eng.3[10%]0%
2.2.2.2.4
2D Detector / Event display
Fri 6/15/01Mon 5/5/03  0%
2.2.2.2.4.1
2D Detector / event display prototyping
Fri 6/15/01Thu 8/30/01 Northeastern SW Eng.3[35%]0%
2.2.2.2.4.2
2D Detector / event display development
Fri 8/31/01Fri 3/8/0299Northeastern SW Eng.3[15%]0%
2.2.2.2.4.3
First version of 2D browser
Mon 4/1/02Mon 4/1/02100 0%
2.2.2.2.4.4
2D Detector / event display development
Tue 4/2/02Mon 5/5/03101Northeastern SW Eng.3[15%]0%
2.2.2.3
Detector Interfaces / Shapes
Thu 4/1/99Mon 5/5/03  0%
2.2.2.3.1
GEANT3 interfaces
Mon 5/3/99Tue 6/1/99  0%
2.2.2.3.1.1
Deployment from pre-existing Cmscan code
Mon 5/3/99Tue 6/1/99  0%
2.2.2.3.2
HEP OpenInventor extensions
Thu 4/1/99Wed 12/4/02  0%
2.2.2.3.2.1
Import/build system for HEPVis
Thu 4/1/99Wed 4/28/99 Northeastern SW Eng. 1 [35%]0%
2.2.2.3.2.2
Development of HEPVis classes (FP)
Wed 6/2/99Mon 10/16/00107 0%
2.2.2.3.2.3
Development of HEPVis classes (FFP)
Thu 2/1/01Wed 12/4/02108 0%
2.2.2.3.3
GEANT4 interfaces
Wed 9/12/01Mon 5/5/03  0%
2.2.2.3.3.1
GEANT4 visualization prototype
Wed 9/12/01Tue 2/26/028Northeastern SW Eng.3[20%]0%
2.2.2.3.3.2
GEANT4 visualization program
Mon 4/1/02Mon 4/1/02111 0%
2.2.2.3.3.3
GEANT4 visualization development
Tue 4/2/02Mon 5/5/03112Northeastern SW Eng.3[20%]0%
2.2.2.4
Detector & Event Visualisation M&O
Mon 5/3/99Fri 12/13/02  0%
2.2.2.4.1
Detector & Event Visualisation M&O (FP phase)
Mon 5/3/99Mon 10/16/00  0%
2.2.2.4.2
Detector & Event Visualization M&O (FFP)
Tue 1/2/01Fri 6/1/01 Northeastern SW Eng. 1 [10%]0%
2.2.2.4.3
Detector & Event Visualisation M&O (FFP phase)
Mon 6/4/01Fri 12/13/02116Northeastern SW Eng.3[10%]0%
2.2.2.4.4
Review baseline GUI tool choices
Wed 10/31/01Wed 10/31/01  0%
2.2.3
Interactive Analysis and Presentation
Thu 4/1/99Wed 3/5/03  0%
2.2.3.1
Statistical/Numerical Analysis
Tue 5/18/99Tue 10/31/00  0%
2.2.3.1.1
Mathematical library
Tue 5/18/99Tue 10/31/00  0%
2.2.3.1.2
Minimiser (short/medium-term)
Tue 5/18/99Tue 10/31/00  0%
2.2.3.1.3
Minimiser (medium/long-term)
Tue 5/18/99Tue 10/31/00  0%
2.2.3.1.4
MINUIT / NAG_C wrapper
Tue 5/18/99Tue 10/31/00  0%
2.2.3.1.5
C++ Fitting API to GEMINI
Tue 5/18/99Tue 10/31/00  0%
2.2.3.2
Histograms / tags
Tue 5/18/99Tue 10/31/00  0%
2.2.3.2.1
Histograms
Tue 5/18/99Tue 10/31/00  0%
2.2.3.2.2
Tags / ntuple extension
Tue 5/18/99Tue 10/31/00  0%
2.2.3.3
Plotting
Thu 4/1/99Tue 10/31/00  0%
2.2.3.3.1
1D and 2D plotting (IRIS Explorer)
Thu 4/1/99Wed 4/28/99 Northeastern SW Eng. 1 [20%]0%
2.2.3.3.2
1D and 2D plotting (HepInventor)
Thu 4/1/99Wed 4/28/99 Northeastern SW Eng. 1 [20%]0%
2.2.3.3.3
Scientific vector
Mon 5/3/99Fri 5/28/99 Northeastern SW Eng. 1 [10%]0%
2.2.3.3.4
1D plotting (SciPlot)
Mon 5/3/99Fri 6/25/99 Northeastern SW Eng. 1 [10%]0%
2.2.3.3.5
1D plotting (Qwt)
Thu 7/1/99Fri 7/23/99 Northeastern SW Eng. 1 [10%]0%
2.2.3.3.6
1D and 2D plotting (IgPlotter)
Mon 8/2/99Thu 1/13/00 Northeastern SW Eng. 1 [10%]0%
2.2.3.3.7
1D and 2D plotting (Qplotter)
Mon 4/3/00Tue 10/31/00  0%
2.2.3.3.8
Surface function plotting
Mon 11/8/99Thu 1/13/00 Northeastern SW Eng. 1 [10%]0%
2.2.3.4
Interactive analysis
Mon 6/7/99Wed 3/5/03  0%
2.2.3.4.1
Database access modules
Mon 6/7/99Fri 7/30/99 Northeastern SW Eng. 1 [10%]0%
2.2.3.4.2
Metadata browser
Mon 2/7/00Fri 4/28/00 Northeastern SW Eng. 1 [20%]0%
2.2.3.4.3
HTL browser
Mon 8/2/99Fri 9/24/99 Northeastern SW Eng. 1 [10%]0%
2.2.3.4.4
Generic Tag browser
Mon 9/27/99Thu 7/13/00141Northeastern SW Eng. 1 [10%]0%
2.2.3.4.5
GUI API to HepFitting
Mon 2/7/00Fri 4/28/00 Northeastern SW Eng. 1 [10%]0%
2.2.3.4.6
Scripting (GUI for Lizard)
Mon 7/3/00Fri 7/28/00 Northeastern SW Eng. 1 [30%]0%
2.2.3.4.7
Lizard "PAW replacement" application
Mon 8/7/00Fri 6/8/01  0%
2.2.3.4.7.1
Evaluation of pre-release
Mon 8/7/00Fri 8/25/00 Northeastern SW Eng. 1 [40%]0%
2.2.3.4.7.2
Evaluation of pre-release
Mon 8/28/00Fri 10/13/00146Northeastern SW Eng. 1 [15%]0%
2.2.3.4.7.3
Release of first version
Mon 10/16/00Mon 10/16/00147 0%
2.2.3.4.7.4
Evaluation of Lizard "PAW functionality" release
Mon 4/16/01Fri 6/8/01374Northeastern SW Eng. 1 [10%]0%
2.2.3.4.8
Data browsers / utilities
Wed 11/1/00Wed 3/5/03  0%
2.2.3.4.8.1
Consolidation of code from "Functional Prototype"
Wed 11/1/00Mon 1/1/01373Northeastern SW Eng. 1 [45%]0%
2.2.3.4.8.2
Consolidation of code from Functional Prototype
Mon 4/23/01Fri 6/1/01 Northeastern SW Eng. 1 [10%]0%
2.2.3.4.8.3
Data browsers for CARF/ORCA/OSCAR
Mon 6/4/01Fri 7/20/01152Northeastern SW Eng. 1 [35%]0%
2.2.3.4.8.4
Data browsers for CARF/ORCA/OSCAR
Mon 7/23/01Fri 8/24/01153Northeastern SW Eng. 1 [45%]0%
2.2.3.4.8.5
Data browsers for CARF/ORCA/OSCAR
Mon 8/27/01Fri 1/25/02154Northeastern SW Eng. 1 [45%]0%
2.2.3.4.8.6
Data browsers for CARF/ORCA/OSCAR
Fri 1/25/02Fri 1/25/02153,155 0%
2.2.3.4.8.7
Data browsers for CARF/ORCA/OSCAR
Mon 1/28/02Wed 3/5/03156Northeastern SW Eng. 1 [45%]0%
2.2.3.5
Interactive Analysis M&O
Mon 5/3/99Fri 12/27/02  0%
2.2.3.5.1
Interactive Analysis M&O (FP phase)
Mon 5/3/99Fri 11/10/00 Northeastern SW Eng. 1 [10%]0%
2.2.3.5.2
Interactive Analysis M&O (FFP phase)
Tue 1/2/01Fri 6/1/01 Northeastern SW Eng. 1 [10%]0%
2.2.3.5.3
Interactive Analysis M&O (FFP phase)
Mon 6/4/01Fri 12/27/02160Northeastern SW Eng. 1 [10%],Northeastern SW Eng.3[10%]0%
2.2.4
IGUANA Infrastructure
Mon 5/3/99Fri 12/27/02  0%
2.2.4.1
Code management
Mon 5/3/99Mon 10/16/00  0%
2.2.4.1.1
IGUANA repository
Mon 5/3/99Fri 5/28/99 Northeastern SW Eng. 1 [10%]0%
2.2.4.1.2
Build, release, distribution system
Mon 5/3/99Mon 10/16/00 Northeastern SW Eng. 1 [10%]0%
2.2.4.1.3
Standalone remote distributor
Mon 11/29/99Thu 1/13/00 Northeastern SW Eng. 1 [10%]0%
2.2.4.2
Code quality / checking
Mon 7/3/00Fri 11/24/00  0%
2.2.4.2.1
Dependency checking
Mon 7/3/00Fri 11/24/00 Northeastern SW Eng.2[25%]0%
2.2.4.3
Documentation Systems
Wed 6/16/99Fri 6/23/00  0%
2.2.4.3.1
Reference documentation system
Wed 6/16/99Mon 8/2/99 Northeastern SW Eng. 1 [10%]0%
2.2.4.3.2
WWW pages builder
Mon 4/3/00Wed 5/3/00  0%
2.2.4.3.3
User guide builder
Mon 5/1/00Fri 6/23/00 Northeastern SW Eng.2[25%],Northeastern SW Eng. 1 [5%]0%
2.2.4.4
IGUANA Infrastructure M&O
Mon 5/3/99Fri 12/27/02  0%
2.2.4.4.1
IGUANA Infrastructure M&O (FP phase)
Mon 5/3/99Tue 12/5/00 Northeastern SW Eng. 1 [10%]0%
2.2.4.4.2
IGUANA Infrastructure M&O (FFP phase)
Mon 6/4/01Fri 12/27/02174Northeastern SW Eng. 1 [10%],Northeastern SW Eng.3[10%]0%
2.3
Distributed Data Management and Processing
Wed 1/6/99Fri 5/21/04  0%
2.3.1
Planning and Interaction
Thu 11/1/01Mon 1/5/04  0%
2.3.1.1
Creation of Grid Implementation Plan
Thu 11/1/01Wed 1/23/02 Caltech SW Eng.1[25%]0%
2.3.1.2
Release of Grid Implementation Plan
Thu 1/24/02Thu 1/24/02178 0%
2.3.1.3
Tracking and Assesment
Fri 1/25/02Thu 1/2/03179Caltech SW Eng.1[10%]0%
2.3.1.4
Assessment and Recommendations Document Phase 1
Fri 1/3/03Fri 1/3/03180 0%
2.3.1.5
Tracking and Assessment
Mon 1/6/03Fri 1/2/04181Caltech SW Eng.1[10%]0%
2.3.1.6
Technical Design Review
Mon 1/5/04Mon 1/5/04182 0%
2.3.2
Computing Complexity Progression
Mon 5/1/00Fri 5/21/04  0%
2.3.2.1
Deployment on CERN cluster
Mon 5/1/00Thu 6/1/00  0%
2.3.2.2
Use of 100 CPU's for Production
Fri 6/2/00Fri 6/2/00185 0%
2.3.2.3
Deployment and Diagnosis
Mon 6/5/00Fri 10/20/00186 0%
2.3.2.4
Use of 150 CPU's for Production
Mon 10/23/00Mon 10/23/00187 0%
2.3.2.5
Deployment and Diagnosis
Tue 10/24/00Mon 7/30/01188 0%
2.3.2.6
Use of 200 CPU's for Production
Tue 7/31/01Tue 7/31/01189 0%
2.3.2.7
Deployment and Diagnosis
Wed 8/1/01Tue 5/7/02190Princeton SW Eng.1[25%]0%
2.3.2.8
Use of 300 CPU's for Production
Wed 5/8/02Wed 5/8/02191 0%
2.3.2.9
Deployment and Diagnosis
Thu 5/9/02Wed 5/14/03192 0%
2.3.2.10
Use of 450 CPU's in Production
Thu 5/15/03Thu 5/15/03193 0%
2.3.2.11
Deployment and Diagnosis
Fri 5/16/03Thu 5/20/04194 0%
2.3.2.12
Use of 600 CPU's (50% Complexity)
Fri 5/21/04Fri 5/21/04195 0%
2.3.3
Distributed Process Management
Mon 11/1/99Wed 6/11/03  0%
2.3.3.1
Distributed Process Management R&D
Mon 11/1/99Wed 11/6/02  0%
2.3.3.1.1
Task Scheduling Development
Mon 11/1/99Fri 4/14/00  0%
2.3.3.1.2
Integration Test with ORCA and 32 Processors
Mon 4/17/00Mon 4/17/00199 0%
2.3.3.1.3
Task Scheduler Development for scalability
Tue 4/18/00Fri 1/5/01200 0%
2.3.3.1.4
Basic Functionality on Tier2 Prototype Center
Mon 1/8/01Mon 1/8/01201 0%
2.3.3.1.5
Task Scheduling Development
Tue 1/9/01Tue 5/1/01202 0%
2.3.3.1.6
Hierarchical Scheduler Scheme Design
Wed 5/2/01Wed 5/2/01203 0%
2.3.3.1.7
Hierarchical Schedule Development
Thu 5/3/01Wed 7/11/01204Caltech SW Eng.2 [25%]0%
2.3.3.1.8
Integration of Globus and GDMP
Thu 7/12/01Wed 8/29/01205 0%
2.3.3.1.9
Release of Task Scheduler with Globus and GDMP
Thu 8/30/01Thu 8/30/01206 0%
2.3.3.1.10
Development of Data Aware Scheduling
Fri 8/31/01Fri 11/16/01207 0%
2.3.3.1.11
Release of Data-Aware Scheduler Design
Mon 11/19/01Mon 11/19/01208 0%
2.3.3.1.12
Implementation of SONN Scheduling Algorithms
Tue 11/20/01Mon 12/3/01209 0%
2.3.3.1.13
Task Scheduler Development
Tue 12/4/01Mon 2/25/02210 0%
2.3.3.1.14
Task Scheduling Integration with Condor
Tue 2/26/02Mon 7/1/02211 0%
2.3.3.1.15
Release of Task Scheduler Functionity for use in Condor
Tue 7/2/02Tue 7/2/02212 0%
2.3.3.1.16
Task Scheduler M&O
Wed 7/3/02Wed 11/6/02213 0%
2.3.3.2
CMS Distributed Process Management Prototyping
Tue 1/1/02Wed 6/11/03  0%
2.3.3.2.1
Technology Evaluation
Tue 1/1/02Mon 2/18/02 Caltech SW Eng.2 [25%]0%
2.3.3.2.2
Technical Recommendation
Tue 2/19/02Tue 2/19/02216 0%
2.3.3.2.3
Testing and Deployment
Wed 2/20/02Tue 4/16/02217Caltech SW Eng.2 [25%]0%
2.3.3.2.4
Design Review
Wed 4/17/02Wed 4/17/02218 0%