Activities
| Task |
Responsible |
Issues |
Status |
- Agree on timeline and program of work
- Basic Acknowledgement of tasks and expected dates.
- Deliverable: E-mail confirmation from all participants that they agree with the work and expected delivery dates assigned to them
|
ALL |
None |
Done |
- Establish List of Prioritized Events for Digitization (PRS) (A1)
- As it is probably not possible to have 50M events digitized in time for the data challenge, the PRS groups should priority order the sample
- Deliverable: List identifying the 30M highest priority events delivered to the production manager. If there is a preference for the order the remaining 40M simulated events are digitized, it should be included.
|
PRS |
None |
Done |
- Identify Regional Center Contributions to DC04 (ALL) (A16)
- Identify participating regional centers and contact information. DC04 requires at least three prototype Tier1 facilities in addition to the Tier0 center.
- Deliverable: E-mail confirmation from participating Tier1 centers expressing interest, identifying contact information, and specifying
- Network Resources between Tier0 and Tier1
- Default transfer protocol (SRB, SRM, GridFTP, etc.)
- Input buffer space available for DC04
- CPU resources available for DC04
- Amount of data that could be handled at the Tier1
Quality of Service expected from critical components |
ALL |
None |
Done |